Project 1 : Supply and installation of main distribution system for the new factory building. Including 3.2MVA, 33KV switchyard, MV & LV Cabling and LV Electrical Panels
Project 2 : Refurbishment of the existing main distribution system of existing factory building (Mill No. 1) Including main LV cabling with cable trunking system for existing feeder cables for tube mill machine
Project 3 : Supply and installation of main distribution system for new tube mill (Mill No. 4) Including main LV cabling and cable trunking system and LV Electrical Panel